1. The Principles of keeping ‘Dirty, Transition and Clean’ when laying out room uses.
2. Early engagement with incumbent providers for specialist systems to inform the design.
3. Ensuring the fabric of the building does not impact on signal strength and connectivity of specialist systems. Ensuring containment routes are designed and installed to facilitate specialist fit out requirements.